Sedco 712

 

sedco712

 

 

After Rig being Cold stacked for 5 years Eurotech were the main Electrical Contractor on the Refurbishment to bring it up to current North sea standards,  we had 70 men employed on the following projects  for approximately 12 months

 

 

 

 

  • Site Survey and reports for new system upgrades and install works
  • Hazardous area Survey and Tagging and Replacement and repair works
  • Compressor Room, Pump room and General lighting upgrades
  • Install new BOP system by ECF
  • Installing new Choke and Kill system by EFC
  • Accommodation HVAC upgrades
  • New Bulk tank system
  • General Cable tray and supports upgrade around Rig
  • Cathodic Protection new system
  • Derrick Lighting and Derrick works upgrade
  • New Drillers Display system
  • New Federal Talk back system
  • Fiber optic cable install around rig
  • Fugro weather monitoring system
  • New Helideck lighting upgrade
  • Pump room Hernis cctv system
  • Hydra-phone upgrade
  • New Transformer HVAC system
  • Watertight door upgrade
  • New life boat Davits and Lighting upgrade
  • Mud Pit motor rewire
  • New Romar system
  • Top Drive service loop install
  • Anchor Winch UPS upgrade
  • Shale Shaker upgrade works
  • Fire Detection upgrade works
  • PA system upgrade works
  • RTO (ready to Operate) punch list to work on
  • DMS upgrade works, including loop testing of all field instrumentation
  • Assisting Rig electrical department on various projects
  • Compressor room new Compressor install